Self-supporting form for arch bridges
Details largest bridge:
- Width on top 10m, width at the base 20,8m
- Span 20,3m, arch length 25,6m
Bridge pier formwork
This large infrastructure job included:
- 4 bridges
- 13 viaducts
- 5 tunnels
Specifications of the piers:
- Width tapered 75cm to 134cm
- Height 6,425m
Formwork for tall viaduct piers
Details piers:
- Tall piles in a hyperstatic structure
- Modular height from 7m to 17,25m
- Thickness adjustable per 100mm from 400mm to 800mm
- Self-compacting high performance concrete
Details formwork:
- No tie-bars through the elements
- Adjustable thickness with saw-tooth coupling
- Hydraulic adjustment of the vertical parts
- Connections between formwork and grade beam
- Box-outs to make chamfered piles
- Maximum concrete pressure 420kN/m²
- Fair-faced finish: no joints, no grout loss, triangular chamfers
- All levels equipped with working platforms
- Wind impact engineering on all configurations
- Foundation frames for positioning of anchors and box-outs
Quai wall formwork
Sea side quay
- Total length 1200m, straight
- Length per phase 23m
- Number of phases 53
- Height wall land side 7000mm
- Height foot 1500mm / 1750mm
- Thickness wall 2160mm / 2800mm
- 2 sets of formwork
- Alternating
- 1 set for even numbers
- 1 set for uneven numbers
- Track width 22,65m
- Height gantry crane 13m
- Weight per set approx. 100T
Land side quay
- Total length 1100m, U-form
- Length per phase 29,39m
- Number of phases 37
- Height wall land side 7000mm
- Height wall water side 2260mm
- Thickness wall 2160mm / 2800mm
- 1 sets of formwork
- Track width 8,1m
- Height gantry crane 15,23m
- Weight per set approx. 100T
Pier formwork
- Columns with a height of 9,2m
- Ground section: 3,3m x 1,15m
Hydraulic climbing circular wall formwork
- Inner diameter 20m, wall thickness 800mm, height 26,5m
- Full circumference inside and outside formwork, poured in one go, height 2m
- Partition wall between dry and wet part of the tank is poured afterwards
- A 1m starter is cast on both ends of the partition wall in phase 1
Formwork for octagonal tanks
Octagonal reactor pits for a drink water production facility
A series of 6 x 5 linked together octagonal tanks:
- 2 outer octagons of which 1 sits against an existing wall
- 3 inner octagons
- Height 6430mm, wall thickness 350mm,
- external faces 2030mm wide, internal faces 1740mm wide
- 1 complete set of formwork + 1 extra inside core
- Inner formwork consisting of 7 corner panels and 1 striking panel
Adjustable formwork and climbing system for twisted walls
The new County Hall in Antwerp is a building with 8 completely twisted levels.
The outside walls of these floors lean back- or forwards. All concrete used is white and the inside of the building needs to be fair-faced. For this purpose, we designed and manufactured a full steel adjustable and twistable formwork without tie-bars through the wall and of which the inside panels have a stainless-steel facing, in order to avoid rust stains.
Technical specifications
- 12 internal panels 720cmm x 410cm
- 4 external panels 720cm x 410cm
- 12 pneumatic vibrators per internal panel
- 3 straight corners
- 4 adjustable twisted corners
- 16 adjustable window forms
- All cut to measure plywood for the windows of the 8 twisted levels
- 2 set-up frames for the window forms
- Crane lifting hook for the panels
- Crane lifting hook for the window forms
- Adjustable climbing frames, 3m and 3,5m wide
Formwork for curved walls with relief
For the Mons railway station, Construx supplies a one-off full steel circular shuttering system with round relief
Both 2 main circular cores and their connecting walls need to be poured on-site. Almost all walls are round, some of which are even round in both directions. All formwork is full steel: steel frame with steel sheeting.
Precast moulds · on-site formwork and scaffolding for viaduct piers
All piers have the same cross-sectional base and rectangular top
Seen the height of the piers varies from 4m to 14m, all vertical ribs have a different inclination.
The 1st stage consists of a viaduct with 34 high piers, poured on-site, after which 2 precast 80T heads are positioned on hydraulic scaffolds. The connection is poured afterwards.
The 2nd stage consists of a viaduct with 14 lower piers. The precast heads are positioned onto a hydraulic scaffold under which the piers are poured.
- Adjustable modular pier formwork
- Hydraulically tiltable and moveable pier head moulds
- Transport yokes for truck and barge
- Internal rebar supports
- External modular rebar scaffolds
- Hydraulic support scaffolds
- Connection form
- Hydraulic frames to hold the heads
PLEASE CONTACT US
Be sure our expertise, accuracy and flexibility will meet your highest standards – your project is in good hands with us!
We’re looking forward to your inquiry!
Headquarters
Manaform GmbH · Siegerlandstr. 35 · D-45770 Marl · Germany
Warehouse
Dieselstr. 21a
D-44805 Bochum
Germany
+49 [0]2365 20 22 678 | +49 [0] 170 66 88 88 1
info@manaform.de
Fax: +49 [0] 2365 20 22 679
MANAFORM GmbH has been the official trading partner of Construx bvba since January 1st, 2020.
We provide consulting services for all frame and system formwork projects in Germany.